KEBUTUHAN ALAT PADA PEKERJAAN GROUND ANCHOR

KEBUTUHAN ALAT PADA PEKERJAAN GROUND ANCHOR
•DATA.
1.Volume = 153 bh
2.Volume / layer = 153 / 3
= 51 bh / layer
HITUNGAN
JUMLAH ALAT DRILLING
1.Waktu Kerja rata rata
= pk. 08.00 s/d pk. 18.00 = 10 jam
2.Kapasitas Drilling alat Ground Anchor / hari = 2 bh
3.Waktu pelaksanaan = 55 hari
4.Volume ground anchore per hari = 153/ 55 = 3.14 bh
Keperluan alat driling = 3.14 / 2 = 1.5 ~ 2 unit
JUMLAH ALAT STRESSING
1. Waktu Kerja rata rata
= pk. 08.00 s/d pk. 18.00 = 10 jam
2. Kapasitas alat stressing / hari = 4 bh
3. Waktu pelaksanaan = 40 hari
4. Volume ground anchore per hari = 153/ 40 = 3.9 bh
Keperluan alat stressing = 3.9 / 4 = ~ 1 unit

4 comments:

Anonymous said...

strutting apaan sih mas...

Anonymous said...

Good post.

Anonymous said...

selamat sore.
bisa di post juga tentang spesifikasi masing2 alat-alat pekerjaan ground anchor gak?
terima kasih...^^

bayu_nugr said...

Terima kasih, ikut ngopi ya